Peregrino |
Client: Kerr McGee, Anadarko, Statoil
|



|
| Project Timeline: Ongoing |
| WJM Project Manager: Gordon Gamble |
Scope of Work:
-
WJM engineered and managed the refurbishment of both drill rigs
-
Project kicked off with Kerr McGee in 2006
-
Project transferred ownership from Anadarko to StatoilHydro in 2008
-
WJM on site at Kiewit Offshore in Corpus Christi, Max Welders in Houma, LA and ESI in Houma, LA from January '07 to December '09
-
Mechanical, process and electrical design elements
-
Procurement of new equipment
-
Refurbishment of existing equipment
-
WJM is providing ongoing engineering support through 2010.
-
WJM is providing a 15 man team for commissioning services for topsides and drill rigs offshore Brazil through 2010.
|
| Greatest Challenge: Multiple changes in operating partner with differing requirements. |
|